The City and County of Denver is planning stormwater pipe and infrastructure improvements beginning at Lollipop Lake in Garland Park and the Cherry Creek waterway and ending at E. Tennessee Avenue and S. Oneida Street. The goals of this project are to decrease property damage due to local flooding; increase pedestrian and driver safety during storm events; and improve water quality for stormwater runoff into Lollipop and Cherry Creek. This storm drain infrastructure is being built in four phases, beginning at the "downstream" end of stormwater flow (Lollipop Lake in Garland Park and the Cherry Creek waterway), continuing along Mississippi Avenue to the "upstream" end at E. Tennessee Avenue and S. Oneida Street.
What to Expect During the Work
Underground drainage installation along Monaco Parkway traffic Stormwater drain installation under Monaco Parkway at Mississippi Avenue Newly installed underground stormwater drainage system below Mississippi Avenue Aerial photo of stormwater pipe installation under Mississippi Avenue New roadway on Kearney Street in Garland Park Kearney Street paving in Garland Park
Underground drainage installation along Monaco Parkway traffic
Stormwater drain installation under Monaco Parkway at Mississippi Avenue
Newly installed underground stormwater drainage system below Mississippi Avenue
Aerial photo of stormwater pipe installation under Mississippi Avenue
New roadway on Kearney Street in Garland Park
Kearney Street paving in Garland Park
Lowering of 72" water transmission conduit in Monaco.
Garland Park and Lollipop Lake aerial from the North
Timeline
Council District: 5, 6 Neighborhood: Washington Virginia Vale
Project Email:info@tennoneida.com Project Hotline:(720) 439-9110 DOTI Construction Project Manager:Aaron McMichaelaaron.mcmichael@denvergov.org DOTI Design Project Manager: Sam Pavone sam.pavone@denvergov.org Contractor:TBD
A pre-construction virtual community meeting for Phase 2 of this project was conducted April 24, 2024. This presentation includes an overview of the work being done, travel impacts associated with the work and the project timeline.
A pre-construction virtual community meeting was held on November 10, 2022 to provide an overview of the Tennessee and Oneida Stormwater Project construction plans, timeline, and travel impacts.