E. Tennessee Ave. and S. Oneida St. Stormwater Project / Phase 3
This City and County of Denver wastewater project brings stormwater pipe and infrastructure improvements to the neighborhood. The project, which is divided into four separate phases, began at Lollipop Lake in Garland Park and the Cherry Creek waterway, and will end at E. Tennessee Ave. and S. Oneida St. Phases one and two have been completed. The goals are to mitigate property damage due to local flooding, increase pedestrian and driver safety during storm events, and improve water quality for stormwater runoff into Lollipop and Cherry Creek.
Phase 3 Construction Updates
MAY 29, 2026
NEW START DATE
Due to some required permitting, the work is now scheduled to begin in early July. We will continue to keep you posted on the timeline.
VIRTUAL COMMUNITY MEETING LINK
Please join us on Tuesday, June 9th, at 6 PM for the virtual community meeting. The project manager will explain the process, schedules, and impacts. You will be able to ask questions via chat. Here’s the link to join: https://bit.ly/tennoneida
Where
Work on this third phase will continue on E. Mississippi
Ave., immediately east of S. Monaco St. Parkway
, and continue east to S. Oneida St.


When
The work will begin in late June 2026 and may take up to 9 months.
Anticipated Travel & Pedestrian Impacts
• We will work closely with all residents to make these impacts as manageable as possible.
• There will be a full closure of E. Mississippi
Avenue in four traffic closure segments; however, crews will only occupy two traffic closure segments at a time. (See map below)
• There will be on-street parking restrictions along E. Mississippi
Avenue and S. Oneida Street. Housing access will remain accessible throughout the work, although alternative parking and alternate access routes will be required.
• Housing access will remain accessible throughout the work, although alternate access routes will be required.
• Some garages facing the work zone will be affected.
• Pedestrian access will be maintained.
• Vehicle detours will be set up around the active work area.
• Work hours are Monday through Friday from 7:00 a.m. to 7:00 p.m. Saturday work will take place intermittently through completion.
• Temporary RTD Route changes — updates to RTD impacts will be posted on this page.
Project Phases
Phase 1: Work consisted of replacing the existing outfall from Lollipop Lake to Cherry Creek, a new outfall into Lollipop Lake, construction of a water quality vault in S Kearny St, and installation of a new 8’ X 7’ pre-cast concrete box culvert from the new Lollipop Lake outfall to the intersection of S. Kearney St. and E. Mississippi
Ave. This phase was completed in 2023.
Examples of Phase 1 Work:
Construction of outfall on Cherry Creek
Construction of outfall on Cherry Creek
Finished outfall along Cherry Creek
Construction of Outfall into Lollipop Lake
Construction of Lollipop Lake Outfall
Construction of Water Quality Structure
Phase 2: Work consisted of relocating the existing 8” sanitary main on E. Mississippi
Ave. from S. Leyden St. to S. Monaco St. Parkway
, installation of new 8’ X 7’ pre-cast concrete box culvert on E. Mississippi
Ave. to S. Monaco St. Parkway
, the lowering of a Denver Water 72” conduit in S. Monaco St. Parkway
and new inlet structures, asphalt paving and ADA ramps on E. Mississippi
Ave. from S. Kearney St. to S. Monaco St. Parkway
. This phase was completed in 2025.
Examples of Phase 2 Work:
Underground drainage installation along Monaco Parkway traffic
Stormwater drain installation under Monaco Parkway at Mississippi Avenue
Newly installed underground stormwater drainage system below Mississippi Avenue
Aerial photo of stormwater pipe installation under Mississippi Avenue
New roadway on Kearney Street in Garland Park
Kearney Street paving in Garland Park
Phase 3: Work will consist of relocating the existing 8” sanitary main on E. Mississippi
Ave, installation of the new 8’ X 7’ pre-cast concrete box culvert from S. Monaco St. Parkway
to S. Oneida St., new inlet structures, associated Denver Water service and main relocations/lowerings, new asphalt paving on E. Mississippi
Ave. from S. Monaco St. Parkway
to S. Oneida St., new concrete curb/gutter, sidewalk, driveway cuts on the south side of E. Mississippi
Ave. from S. Monaco St. Parkway
to S. Oneida St., and new ADA ramps at the intersection of E. Mississippi
Ave. and S. Oneida St. Phase 3 is scheduled to begin in June 2026.
Phase 4: When funding is secured, Phase 4 will be the final phase of this project. The project will continue on S. Oneida St. from E. Mississippi
Ave. with installation of a new 8’ X 7’ pre-cast concrete box culvert for about 300’ on S. Oneida St., transitioning to a 10’ X 5’ pre-cast concrete box culvert up to approximately 300' north of the S. Oneida St. and E. Tennessee Ave. intersection. Start date TBD.
Project Segment Map
Lollipop Lake, Garland Park, and Cherry Creek Outfall

Garland Park and Lollipop Lake aerial from the North

Garland Park and Lollipop Lake aerial from the West.