West Jewell Avenue Bicycle and Pedestrian Bridge

Photo explaining the updates to the west Jewell Avenue Bicycle and Pedestrian Bridge

The Department of Transportation and Infrastructure has known that the desire for a bicycle and pedestrian bridge over Santa Fe Drive/US 85 and the adjacent freight railroad and RTD light rail tracks near West Jewell Avenue has been more than a decade in the making. The need for a safe, grade separated crossing to provide east-to-west connectivity for pedestrians and bicyclists is identified in several City plans, and this high-priority project received funding through the City and County of Denver’s 2017 Elevate Denver Bond Program. Please see more details about this project below:

Who Can You Contact For More Information On This Project?

For more information on this project, please contact:

Katie Gargaro, Project Manager, Department of Transportation & Infrastructure at: katie.gargaro@denvergov.org

For project questions or concerns, email abi.subramanian@denvergov.org.

What Is This Project?

The City of Denver alongside it's residents and the Department of Transportation and Infrastructure have vocalized the need for a bridge that supports both pedestrians and bicycles at West Jewell Avenue. The planned improvements are: 

  • Bridge providing improved safety and mobility for pedestrians and bicyclists between Pasquinel's Landing park, the Platte River Trail and south Broadway corridors
  • ADA-compliant design
  • Better bicycle connection to RTD’s Evans Station
  • Bridge landings on both sides of Santa Fe Drive
  • Associated landscaping improvements
  • Engineering design coordination with the Iowa Underpass Bicycle/Pedestrian Improvements project

When Did This Project Start and When Will It End?

The West Jewell Avenue Bicycle and Pedestrian Bridge began on design in Q3 of 2021. The Department of Transportation and Infrastructure plans to have substantial completion done by Q4 2026. For a list of key dates, please see below the information the Department of Transportation and Infrastructure has provided. 

Project Status: Design

Project Timeline

Q3 2021: Begin Design

Q2 2023: Right-of-Way Acquisition

Q1 2023: CM/GC Procurement

Q3 2024: Start of Construction

Q4 2026: Substantial Completion


Council District: 7

Neighborhoods: Ruby Hill and Overland Park

Where Can I Find A Presentation On This Subject?

Although this is a bit dated being from 2019, the Department of Transportation and Infrastructure has published a PDF going over the details of this project called the Jewell Avenue Pedestrian Bridge Conceptual Alignment and Constraints Design Analysis Report, you can view that HERE:

We also recommend to check the main project website for more information HERE:

They also have provided a project map which will be visible here:Image of the changes being made for the Jewell and Evans Bicycle and Pedestrian Bridge Area Map

How Can I Track Changes Made To This Project?

NOTE: DOTI CONSTANTLY CHANGES THEIR INFORMATION PLEASE MAKE SURE TO STAY UP TO DATE ON THEIR SITE

 

We recommend to check the project website HERE:

You can also view the overview of all projects at the website HERE: