1.1 Implement a process to convert change orders into contract amendments – Working with the Mayor’s Office, the Department of Transportation & Infrastructure should add context to Executive Order No. 8 to determine whether the City Council should be required to approve change orders for contracts that already exceed $500,000 when the change order is of high value, and to develop a process to identify when a change order alters an agreement beyond the scope of a change order.
Transportation & Infrastructure should also work with the City Attorney’s Office and other stakeholders to update the city’s “Standard Specifications for Construction General Contract Conditions” to identify when a change order alters an agreement beyond the scope of a change order.
Relevant change orders should then be converted to amendments and approved by the City Council accordingly.
Department of Transportation & Infrastructure – Disagree
1.2 Formalize the relationship between the department and the City Council – Working with the City Council, the Department of Transportation & Infrastructure should formalize what should be reported beyond legal requirements like agreements and amendments to the City Council member in whose district the project is located and to the City Council’s Transportation & Infrastructure Committee. This should, at a minimum, include project delays and cost overruns.
Department of Transportation & Infrastructure – Agree, Implementation Date – Feb. 26, 2027
1.3 Update general contract guidance – The Department of Transportation & Infrastructure should work with the City Attorney’s Office and other stakeholders to update the city’s “Standard Specifications for Construction General Contract Conditions” to:
- Incorporate current and leading practices.
- Clarify whose approvals are necessary to comply with separation of duties.
- Formalize the change-order comment process.
- Address impacts from alternative delivery methods including those the city typically uses like design-build and construction manager/general contractor.
Department of Transportation & Infrastructure – Agree, Implementation Date – Feb. 26, 2027
2.1 Address Denver’s historic brick sewer system – The Department of Transportation & Infrastructure should work with the Colorado State Historic Preservation Office to determine whether a citywide programmatic agreement may be created to proactively address the potential discovery of brick sewers during federally-funded construction projects.
At a minimum, future federally-funded projects involving subsurface construction should include historic brick sewers in the National Environmental Protection Act review in coordination with the Section 106 evaluation process.
Department of Transportation & Infrastructure – Agree, Implementation Date – Feb. 26, 2027
2.2 Use a formal project delivery selection methodology – The Department of Transportation & Infrastructure should ensure the project delivery method it selects aligns with the project by creating and implementing a formalized project delivery selection methodology based on leading practices, like those developed by the Colorado Department of Transportation, University of Colorado, Water Collaborative Delivery Association, and other similarly credible sources.
The project delivery selection methodology should adequately consider common alternative delivery methods like:
- Design-build.
- Construction manager/general contractor.
After following the selection methodology, staff should document the process followed, the delivery method selected and retain those documents in accordance with the city’s retention policies.
Department of Transportation & Infrastructure – Agree, Implementation Date – Feb. 26, 2027
2.3 Strengthen the department’s internally-developed project delivery selection methodology – The Department of Transportation & Infrastructure should continue refining and strengthening its adapted project delivery selection methodologies to ensure they align with leading practices already established by the Colorado Department of Transportation, University of Colorado, Water Collaborative Delivery Association, or other similarly credible sources.
Department of Transportation & Infrastructure – Agree, Implementation Date – Feb. 26, 2027
2.4 Ensure a competitive bidding process for capital projects by retaining documentation of all steps – The Department of Transportation & Infrastructure should ensure future capital projects preserve records in accordance with the city’s records retention schedule to demonstrate a competitive bidding process. This process should include:
- Ensuring all steps identified in future requests for qualifications and requests for proposals are completed.
- Developing a process to reassess risks should a bidder choose to withdraw.
- Documenting these processes formally.
- Following the city’s retention rules and keeping all bidding documentation, like proposal scorings, to ensure transparency around the competitive bid selections.
Department of Transportation & Infrastructure – Agree, Implementation Date – Feb. 26, 2027
2.5 Implement subcontracting-process oversight controls – The Department of Transportation & Infrastructure should require submission and retention of subcontract and bidding documentation to support costs validation and ensure change orders are independently reviewed for reasonableness and proper authorization.
Transportation & Infrastructure should also implement controls to oversee the subcontracting process, including requiring review and approval of subcontract agreements and any significant revisions, to comply with city subcontracting policies in the “Standard Specifications for Construction General Contract Conditions” guidance.
Department of Transportation & Infrastructure – Disgree
3.1 Strengthen quality oversight processes, ensure contract compliance, and formalize nonconformance reporting – The Department of Transportation & Infrastructure should strengthen its documentation and the ability to trace its quality oversight and contract compliance processes by:
- Requiring consistent documentation.
- Implementing procedures to link nonconformance reports and other quality-issue tracking processes to payment applications and schedule of value line items.
- Documenting it has received required insurance coverages and waivers of subrogation.
- Documenting verification of activities or progress supporting payment approvals.
- Establishing standardized documentation requirements to ensure verification, acceptance, and payment decisions are fully supported and auditable.
Transportation & Infrastructure should work with the City Attorney’s Office and other stakeholders to update the city’s “Standard Specifications for Construction General Contract Conditions” to include formalized procedures for nonconformance reporting requirements and contract compliance.
Department of Transportation & Infrastructure – Disgree
3.2 Enforce liquidated damages and update the city’s “Standard Specifications for Construction General Contract Conditions” – The Department of Transportation & Infrastructure should enforce liquidated damages as allowed by contract terms.
Transportation & Infrastructure should work with the City Attorney’s Office and other stakeholders to update the city’s “Standard Specifications for Construction General Contract Conditions” to include formalized standards and criteria on when liquidated damages can be waived.
Department of Transportation & Infrastructure – Agree, Implementation Date – Feb. 26, 2027