Project Updates - April 2011
PROJECT CONSTRUCTION UNDERWAY

Castle Rock Construction has begun work on the City and County of Denver’s project to widen 56th Avenue from Spruce Street to Havana Street.

Early project activities have included the relocation of fences in the corridor and earthwork grading.  Construction of a new bridge over the haul road and the widening of the bridge over the Havana Channel are underway. Construction of the new westbound lanes in concrete pavement for 56th Avenue is scheduled to be completed by the end of the June. When concrete pavement is completed, two-way traffic will be shifted to the new lanes and reconstruction of the new eastbound lanes will begin.

 

In a concurrent project, Xcel Energy is testing and upgrading a major natural gas line in the corridor.

 



For project information, please contact
Jess Ortiz, PE
City and County of Denver
Capital Projects Management
720-8913-0781
jess.ortiz@denvergov.org  