Progress Report
Better Denver logo The Better Denver Bond Program continues to make great progress with 239 of 317 Better Denver Bond projects completed (through Q3 2011). Over 88% of Bond Projects are now either in construction or completed.  All this work represents an injection of over $420 million into the local economy which is providing a boost for jobs.  2011 is the most significant period of the Bond Program in terms of the planned value of major projects being executed.


A summary of our program progress through the last quarterly reporting period (Q3 2011) is shown below and in the Q3 2011 report.  

  

Status through 3rd Quarter (June 1 - September 30, 2011)

Number of Projects by Phase  

Project Phase

Number of Projects

Future Projects

15

In Planning Phase

1

In Design Phase

17

In Construction Phase

41

Project Complete 

239

Post Program (after 2012)

4

Total Number of Projects

317

 “Projects” refers to the current total number of projects and sub-projects that comprise the Program

 


 

 




spacer
spacer
Completed Bond Projects
Click here to view a full list of all completed bond projects through the current reporting quarter.
spacer
spacer
2011 Third Quarter Report
This report outlines the progress of the Better Denver Program
in the 2011 Third Quarter Report.
 