spacer
TopL
spacer
spacer
Progress Report
Better Denver logo The Better Denver Bond Program continues to make great progress with 266 of 318 Better Denver Bond projects completed (through Q1 2012). Over 90% of Bond Projects are now either in construction or completed.  All this work represents an injection of over $430 million into the local economy which is providing a boost for jobs.  2011 was the most significant period of the Bond Program in terms of the planned value of major projects being executed.


A summary of our program progress through the last quarterly reporting period (Q1 2012) is shown below and in the Q1 2012 report.  

  

Status through 1st Quarter (January 1 - March 31, 2011)

Number of Projects by Phase  

Project Phase

Number of Projects

Future Projects

3

In Planning Phase

2

In Design Phase

19

In Construction Phase

24

Project Complete 

266

Post Program (after 2012)

4

Total Number of Projects

318

 “Projects” refers to the current total number of projects and sub-projects that comprise the Program

 
 
spacer
spacer
Completed Bond Projects
Click here to view a full list of all completed bond projects through the current reporting quarter.
spacer
spacer
2011 Fourth Quarter Report
This report outlines the progress of the Better Denver Program
in the 2012 First Quarter Report.
 
spacer
spacer
Project Status Map
Click map to enlarge
 
TopR
BottomL
BottomM
BottomR