WELCOME
Structures are popping up all along the corridor, as DTCG’s
crews continue construction of the West Corridor light rail
project. Now, more than ever, it’s important to keep abreast
of construction activities and traffic impacts. By becoming a
subscriber to our e-newsletter, you will get the most
up-to-date information. To subscribe to the newsletter or to
familiarize yourself with the tools available to you on the
West Corridor Web site, click
here.
IS IT
DRY GULCH? IS IT LAKEWOOD GULCH? IS IT LAKEWOOD/DRY
GULCH?
In past articles, we’ve talked about the gulch area
(In Denver between Federal and Sheridan) and the water
they carry. But where are Dry Gulch and Lakewood Gulch
located and where do they meet at a confluence and
continue toward the Platte River?
Dry Gulch begins at roughly 12th Avenue and Yates
Street while Lakewood Gulch begins at approximately 9th
Avenue and Xavier Street. They both follow their own
paths until they merge at 12th Avenue and Perry Street.
The confluence of the two (Lakewood/Dry Gulch) continues
to approximately 12th Avenue and Newton Street where
once again it becomes Lakewood Gulch. Lakewood Gulch
then continues eastward to the Platte River. To see a
map of the gulches, click
here. |
FEDERAL
BRIDGE
Denver Transit Construction Group is now in the first
phase of reconstructing the bridge over Lakewood Gulch
and the old Denver, Lakewood and Golden Railway at
Federal Blvd. This is one of three street bridges that
will be rebuilt during construction of the West
Corridor. The degeneration of the bridge is visible
while driving, but the more serious flaws are in the
structure that supports the bridge. Over the years, many
of the concrete supports have fallen away, leaving the
steel reinforcing bars exposed. Built in 1922 and
widened in 1960, the bridge currently carries about
36,000 vehicles per day and is rated as one of the five
worst bridges in the Denver metro area, with a rating of
15.5 out of 100.
What can’t be seen by traveling motorists are the
many utilities running along the underside of this
bridge. Electric, gas, phone and water lines all pass
underneath the bridge and will have to be relocated onto
the new structure. On most major road construction
projects, traffic impacts drive the schedule; but in
this case, utility relocations are the driving force.
Relocations are tedious and time consuming and actually
draw construction of the bridge out longer than would be
required to simply build the bridge.
Construction is currently visible on the west side of
Federal, as crews have already set some concrete
abutments to widen the structure. Once all the abutments
are in place, crews will place girders, pour the deck
and divert traffic onto the new structure. Then the
utility relocations will begin, followed by the
demolition of the old bridge. Once it’s demolished,
construction on the second half of the bridge will
follow. The final phase will be connecting the two
sections. Current scheduling indicates construction on
this bridge will continue into 2011. The photo below
depicts original construction of the bridge in
1922. |
COLORADO SCHOOL OF MINES
PARTNERSHIP
Students from the Colorado School of Mines are
working on the Federal Highway Administration’s (FHWA’s)
Exploratory Advanced Research (EAR) Program. Initiated
in 2008, the study is being conducted by the Colorado
School of Mines with the participation of roller
manufacturers and the Colorado and Minnesota Departments
of Transportation. The study, “Development of Soil
Stiffness Measuring Device for Pad Food Roller
Compactor” is intended to help develop a machine that
will “walk out” onto the soil and extract soils of
different moisture levels to ensure their proper use.
The Colorado School of Mines role is to study soils and
develop and analyze field data to refine the model.
Denver Transit Construction Group worked with the
students to provide soil samples for analysis. If
successful, the project will be a significant leap
forward to ensure quality during earthwork construction
and improve compacting practices resulting in longer
pavement life and lower costs. |
CONSTRUCTION UPDATE – AREA 1
(Jeffco Government Center to Denver Federal
Center)
Current Activities Area 1 is
currently the most active section of the project. Piers
and abutments for the bridges at Colfax Avenue and
Indiana Street are visible. Work on these structures
will be ongoing for several months. By the end of
September, girders will be placed on the light rail
bridge over Colfax. Placement of the girders will
require a complete weekend closure of Colfax Avenue in
the area just west of the 6th Avenue and Colfax
interchange. Traffic control measures and warning signs
will be placed to move traffic around the construction
area and detour routes will be labeled. Crews completed
the excavation of a temporary parking lot on the
northeast side of the Jefferson County Government Center
and electrical installations and pavement activities
there are ongoing. Retaining wall construction is
apparent near the Golden Cemetery and along 6th Avenue
from Indiana east to Union. Utility upgrades and
relocations continue just north of the 6th Avenue
Frontage Road near the Red Rocks Community College. Work
in this location requires lane shifts to the south, but
both directions of traffic are still operational.
Upcoming Activities Work on I-70
is fast approaching; in fact, you may have already
noticed the barriers that are now in place on the median
between the Colfax and 6th Avenue exits. Current
scheduling indicates that work will begin on top of I-70
on September 25, with the initial work being done during
that weekend. Work will then continue (eastbound) during
night time hours for approximately two months. Eastbound
traffic will encounter lane closures from 7:00 p.m. to
5:00 a.m. Sunday through Thursday until the complete
shutdown of I-70 eastbound between the Colfax and 6th
Avenue exits. This shutdown is scheduled on the weekend
of October 16th and 17th. Crews will then move to the
westbound side and continue night time work with lane
closures until the complete closure of westbound traffic
the weekend of November 6th and 7th. Advanced warning
and notification will be visible as the full closures
come closer. Once work on top of I-70 is complete, crews
will move off of the highway and begin digging out the
dirt under I-70 for the light rail
tunnel. |
CONSTRUCTION UPDATE AREA 2
(East of the Denver Federal Center to Sheridan)
Current Activities Utility
relocations continue along the 13th Avenue corridor in
Lakewood and work has begun on the drainage culvert just
east of Simms on Collins Ave. Piers for the bridge over
6th Avenue at the Denver Federal Center are visible and
DTCG’s subcontractor will continue work for several
months in this area. Environmental clearance of the
properties on the north side of 13th Avenue east of
Wadsworth has been completed and demolition of two homes
and one commercial building is scheduled to begin this
week. Once they are demolished, a construction yard in
this area will begin to take shape.
Upcoming Activities Construction
of the light rail bridge over Wadsworth at 13th Avenue
will soon be apparent with drill rigs moving in and
piers being erected. Traffic on Wadsworth should not be
significantly impacted until crews place the girders on
the bridge in late 2009 or early 2010. 13th Avenue just
east and west of Wadsworth is closed for the duration of
construction in the area. Work on drainage culverts on
13th Avenue near Richey Park and at 13th Avenue and
Harlan Street should begin in October. Neither activity
will significantly impact traffic or neighboring
residents until crews get to Carr Street later this
year. Carr will be closed at the 13th Avenue
intersection for a few weeks to pipe under the roadway
for the future culvert. Advanced notification will be
given prior to the closure.
|
CONSTRUCTION UPDATE AREA 3
(East of Sheridan to the Auraria Campus)
Current and Ongoing
Activities Retaining wall construction in
the Gulch continues from Sheridan to Knox Court. Once
the walls at Knox Court are completed, the section of
Knox between 12th Avenue and 13th Avenue will reopen.
Current scheduling indicates the reopening by year’s
end. The Tennyson Pedestrian Bridge is now in place and
you can expect to see the pedestrian bridge at Hazel
Court by the end of September. Phase one of the work on
the Federal Boulevard Bridge continues as more and more
piers become visible against the skyline. The relocation
of a sewer line under Federal was completed this past
weekend. Storm and sanitary sewer relocations and earth
work between Sheridan and Decatur will continue in this
area for the next several months. The bridge at Lakewood
Gulch (just east of Decatur) has not seen any recent
activity, but crews are hoping to place the girders in
October. Once the girders are set, crews will pour the
deck and finalize construction on this bridge. By the
end of September, 12th Avenue between Perry and Osceola
will be reopened. Crews are just finishing up the new
curb, sidewalks and pavement.
For more
information on construction please visit the Construction
Information page on the West Corridor Web
Site. |
PHOTO
GALLERY
Check out the latest photos!
Visit the West
Corridor Photo Gallery on the Web site to see the
latest and greatest construction photos. Not only have
we added new photos throughout the Web site, we are
constantly updating the gallery to feature up to the
minute action photos. There are many categories of
photos to choose from – so sit back, relax and enjoy the
show! |
HOW CAN
I GET (OR STAY) INVOLVED?
One of the best ways to get the latest information on
the West Corridor is to ensure we have your e-mail
address. Our periodic e-mails will provide you with
information essential to being an active participant. As
full construction continues for the next two and a half
years, it is the best way to stay informed of
construction activities. Tell your friends and neighbors
to sign up on our e-mail list to receive up-to-date
information, and if your e-mail changes, please notify
us.
Don’t forget to visit our Web
site, where you’ll find all the latest information
about the West
Corridor. | Where
Can I Get More Information? Web
site: http://www.RTD-FasTracks.com
E
Mail: WestCorridor@RTD-FasTracks.com
Phone: Kathy
Berumen, 303-626-6762 Brenda Tierney,
303-299-2401
|