WELCOME
The recent warm weather has helped keep early construction
work moving on the West Corridor. New activities begin along
the corridor constantly, so it’s important to stay
informed by becoming a subscriber to our e-newsletter. To
subscribe to the newsletter, or to familiarize yourself with
the tools avilable to you, click on The
West Corridor Web site.
CONSTRUCTION
UPDATE
Kipling Walls Construction of the
Kipling MSE walls is progressing rapidly. The low level walls
on the east side are in place and crews have moved to the west
side to begin the same process. While walls are being placed
on the west side of Kipling Street, construction of the
Pikeview tunnel will begin on the east side. This tunnel will
go under the light rail tracks and provide access for bikes
and pedestrians. Construction equipment will continue to move
in and out of the staging areas at the intersection of
Lakewood Heights Drive and Kipling Street and at the corner of
Pikeview and 13th Avenue.
Lakewood Dry Gulch Crews have begun
preparing the gulch area to straighten out the oxbow channel.
This area of the gulch is called the oxbow by virtue of its
U-shaped bend. When seen from the air, it resembles the old
oxbow used on oxen for plowing fields.
The old bridges have been demolished and the area has been
cleared of vegetation. Current construction activities include
excavation, leveling and grading and permanent improvements to
the storm sewer system. Once these upgrades are complete,
crews will begin placing retaining walls adjacent to the new
light rail bridges.
The above ground portion (superstructure) of the pedestrian
bridges at Tennyson Street and Hazel Court are being
fabricated off site and placement is expected in early
summer.
Storm Sewer/Storm Drainage
Upgrades Crews completed improvements to the storm
drainage system on Pierce Street and have moved to the
Jefferson County Government Center. Work on Earl Johnson Road
and the Government Center is being done during evening hours
to minimize impacts to visitors. This activity will continue
through the month of March. Asphalt paving on Earl Johnson
Road will require a weekend closure between 6th Avenue and
10th Avenue on March 14th and 15th.
DTCG and the City of Golden will close Earl Johnson Road
from April 1, 2009 through May 31, 2009 for continued
improvements in that area. Always check the Road
Closures page of the West Corridor Web site for closures
that may affect you.
Crews will begin reconstruction of the water line under
Knox Court on the 23rd of March. This activity will require
the complete closure of Knox Court from 10th Avenue to 13th
Avenue. The closure will remain in effect through July. RTD
and Denver Public School buses have been rerouted to bypass
this closure.
Utility Relocations Qwest, Comcast and
Xcel Energy continue their relocation activities along the
light rail line. To see a current schedule of their utility
relocations, click
here.
TREES IN
PUBLIC RIGHT-OF-WAY
Trees in the public right-of-way must be removed, not only
for the configuration of the West Corridor Light Rail line but
also for construction purposes. Click on the West
Corridor Tree
Removal Fact Sheet to review the long and short-term
reasons for tree removal.
In early March, Denver Transit Construction Group began
identification of trees and vegetation that must be removed.
Trees requiring removal have been marked with a green “X”.
Once marked, public notification to neighboring residents via
door hanger was made. Trees between Oak Street and Sheridan
Boulevard have been marked and crews will begin removing them
from west to east on March 17, 2009. Upon removal, crews will
stockpile the cuttings and plan to make mulch and firewood,
which will be available to residents along the corridor.
Please check the West Corridor Web site often for updates on
the plan for mulch and firewood disbursement.
PERMANENT
STREET CLOSURES
Due to safety and operational issues, several permanent
street closures in Lakewood will take place as the West
Corridor Light Rail line is implemented. The permanent
closures include the light rail trackway (approx 13th Avenue)
at Marshall, Otis, Vance, Allison, Brentwood, Holland and
Nelson. These streets will be closed across the light rail
trackway, but automobiles will still be able to access 13th
Avenue in areas where the street runs prior to the tracks.
Denver Transit Construction Group anticipates the closure
of these streets in early summer. Construction activities will
require truck and heavy equipment access to the right-of-way,
and closing these streets in advance minimizes some of the
traffic impacts expected along 13th Avenue. Signs will be
placed indicating the intent to close prior to the actual
closures.
To see final plans of permenent street closures, click
here.
HOW CAN I GET
(OR STAY) INVOLVED?
One of the best ways to get the latest information on the
West Corridor construction phase is to ensure we have your
e-mail address. Our periodic e-mails will provide you with
information essential to being an active participant. As the
project evolves and develops, it will be important to keep all
members of the community informed on construction activities.
Tell your friends and neighbors to sign up on our e-mail list
to receive up-to-date information, and if your e-mail address
changes, please notify us.
Don’t forget to visit our Web site where you’ll find all
the latest information about the West
Corridor. Where Can I Get More
Information Web site: http://www.RTD-FasTracks.com
E
Mail: WestCorridor@RTD-FasTracks.com
Phone: Kathy
Berumen, 303-626-6762 Brenda Tierney,
303-299-2401
|