WELCOME
The West Corridor project team is gearing up to move into
full construction soon. As soon as next month, the team will
accelerate construction activities in all segments of the
corridor. Now more than ever, it’s important to stay informed
by becoming a subscriber to our e-newsletter. To subscribe to
the newsletter or to familiarize yourself with the tools
available to you on The West Corridor Web site, click
here.
ARBOR
DAY WEEKEND MULCH GIVEAWAY
Residents living between Sheridan Boulevard and Oak
Street and between 6th Avenue and Colfax Avenue will be
eligible to participate in Denver Transit Construction
Group’s Arbor Day mulch giveaway. Trees that have been
removed for construction of the West Corridor were
mulched and will be available for eligible residents to
pick up on a first come/first served basis. This is not
beauty bark, simply wood chips directly from the
trees.
The giveaway will take place at the Quail
construction yard, located at 1305 Quail St. on
Saturday, April 25, 2009. Crews will be on-site from 8
a.m. to 12 p.m. to help residents load their trucks.
Residents must show a current ID that shows proof of
residency within the required boundaries and sign a
general release of liability. DTCG employees will load
the mulch into your vehicle. For more information, click
here. |
CONSTRUCTION UPDATE
Tree Removal As DTCG prepares for
full blown construction, crews have begun to “clear and
grub” areas. This includes the removal of vegetation,
including trees and shrubbery. Trees have been removed
from Nelson Street to Wadsworth Boulevard and in
areas of the Lakewood Dry Gulch. Crews are now moving
west to east to clear only those trees obviously in the
right-of-way. Lakewood Dry
Gulch Work on the channel continues in the
Dry Gulch. Crews have rerouted the first segment of the
channel by installing a ‘Pump Around’ that moves the
water flow out of the work area. The storm sewer
improvements will continue in phases as areas are
complete. The final phase of this work will be the
construction of retaining walls to hold fill back from
the tracks. Kipling
Walls Construction of the MSE walls
continues on both sides of Kipling Street. Construction
of the Pikeview tunnel has also begun, and will continue
through mid-May. This tunnel will go under the light
rail tracks and provide access for bikes and
pedestrians. Traffic impacts in and around the area are
minimal. Jefferson County Government
Center Crews completed the replacement of
the water line under Earl Johnson Road and the parking
lots of the Jefferson County Government Center. DTCG and
the City of Golden anticipate closing Earl Johnson Road
between 6th Avenue and 10th Avenue from May 1 through
June 30 for road improvements in that area. To get
up-to-date information on road closures and traffic
impacts, click
here. Storm Sewer/Storm Drainage
Upgrades Crews are reconstructing the water
line under Knox Court, which requires the complete
closure of Knox Court from 12th Avenue to 13th Avenue.
The closure will remain in effect through July.
Pedestrian access is allowed on the west side of Knox
Court in this location. Right-of-Way
Fencing As RTD’s right-of-way division
purchases land to accommodate the West Corridor light
rail line, vacant properties will be fenced off for
future demolition. Denver Transit Construction Group
will begin this process in late April at Umatilla,
Sheridan and Wadsworth. Crews will not impact traffic
for this activity. Once these areas have been
environmentally inspected and released, RTD will turn
them over to DTCG for demolition. Union
Boulevard The West Corridor will be
crossing under Union Boulevard at 6th Avenue in a
tunnel. To accommodate this, the agricultural ditch on
the south side of 6th Avenue is being relocated. Crews
are currently boring a new path for this ditch under
Union Blvd. The work area has been blocked off on the
west side of Union and in mid-May, as crews move to the
east side, approximately eight parking spaces in the
Cold Springs lot will become unavailable.
Denver Federal Center Denver
Transit Construction Group will be installing a new
security fence north/south along the west side of the
Federal Center from 2nd Avenue to 6th Avenue. This new
fence will put RTD’s work area outside of the confines
of Homeland Security and enable DTCG to set up a storage
and staging area and build a new road that will feed the
light rail station. This activity will start on April 20
but should not impact traffic in the
area. Utility Relocations Qwest,
Comcast and Xcel Energy continue their relocation
activities along the light rail line. To see a current
schedule of their utility relocations, click
here. |
DTCG
SPOTLIGHT
Jon Brazeal is the Project Engineer for DTCG on the
West Corridor project. His duties are vast and
far-reaching and include assuring that the project is
built according to plans and that DTCG completes
construction on time. He is also responsible for working
with the field superintendents to develop the ongoing
schedule and change resolution.
Jon came to DTCG in August, after working 10 years at
Granite Construction in Orange County, California. His
experience includes an array of high profile projects
including the realignment of US20 in Oregon from Pioneer
Mountain to Eddyville. Jon served as the Deputy Project
Manager on this job and facilitated change orders,
managed field and office engineers, project cost
forecasting, long-term planning and scheduling, and
subcontractor management.
Prior to his position in Oregon, Jon worked for
Granite on the HOV widening of SR22 in Orange County.
The work on this project included vertical retaining
walls, bridge widening, bridge replacements, city street
undercrossings and major freeway interchange
improvements.
Jon is a welcome addition to DTCG. His proven track
record of managing large, fast-paced projects and his
extensive experience and integrity will add strength to
DTCG’s management team |
HOW CAN
I GET (OR STAY) INVOLVED?
One of the best ways
to get the latest information on the West Corridor is to
ensure we have your e-mail address. Our periodic e-mails
will provide you with information essential to being an
active participant. As full construction gets underway,
it will be important to keep all members of the
community informed on construction activities. Tell your
friends and neighbors to sign up on our e-mail list to
receive up-to-date information, and if your e-mail
address changes, please notify us.
| Where Can I
Get More Information? Web
site: http://www.RTD-FasTracks.com
E
Mail: WestCorridor@RTD-FasTracks.com
Phone: Kathy
Berumen, 303-626-6762 Brenda Tierney,
303-299-2401
|