DATE: Friday, May 09, 2008 TIME: 11:00 AM
CONTRACT NO.: CE80076 MAIN PROJECT FUNDING NUMBER: PI81608_116
PROJECT NAME: DTC Boulevard Concrete Replacement and Grinding
PROJECT MANAGER: Brian Roecker PHONE: (720) 865-6869
|
|||||||||
|
Engineer’s Estimate: $1,495,575.00 |
||||||||||
|
Prequalification Required: CE-7 $2,500,000.00 |
||||||||||
|
Number of Addenda :1 |
BIDS
|
|||||||||
|
MWBE Goals: 10.00% |
|
|
|
|
|
|
|
|||
|
Bidders: |
New Design Construction Company |
Keene Concrete, Inc. |
K.E.C.I. Colorado, Inc. |
Technology Constructors, Inc. |
Jalisco International, Inc. |
Concrete Works of Co., Inc. |
|
|
||
|
Bid Guarantee Submitted |
þ |
þ |
þ |
þ |
þ |
þ |
|
|
||
|
Addenda Acknowledged |
þ |
þ |
þ |
þ |
þ |
þ |
|
|
||
|
Bidder Disclosure Submitted |
þ |
þ |
þ |
þ |
þ |
þ |
|
|
||
|
Goals met |
|
|
|
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
||
|
TOTAL BID AMOUNT:
|
$1,207,176.50 |
$1,236,110.00 |
$1,369,960.00 |
$1,370,790.00 |
$1,397,625.00 |
$1,445,270.00 |
|
|
||
|
Bid Rank: |