JOHN W. HICKENLOOPERMayor |
BID SUMMARY |
|||||||||
|
City and County of Denver Department of Public Works Contract Administration 201 West Colfax Dept. 611 Denver, CO 80202 |
DATE: Friday, October 02, 2009 TIME: 11:00 AM
CONTRACT NO.: CE90815 MAIN PROJECT FUNDING NUMBER: PZ03609_413
PROJECT NAME: 2009 CITYWIDE CURB, GUTTER & CROSSPAN REPAIR - PHASE 4
PROJECT MANAGER: Rick Zimmat PHONE: (303) 446-3718
|
|||||||||
|
Engineer’s Estimate: $600,000.00 |
||||||||||
|
Prequalification Required: None |
||||||||||
|
Number of Addenda :0 |
BIDS
|
|||||||||
|
SBE Goals: 5.00%
DBE Goals:
MWBE Goals: |
|
|
|
|
|
|
|
|||
|
Bidders: |
Keene Concrete, Inc. |
Fasick Concrete, Inc. |
Noraa Concrete Construction Corp. |
Thoutt Bros. Concrete Contractors, Inc. |
Villalobos Concrete |
|
|
|
||
|
Bid Guarantee Submitted |
þ |
þ |
þ |
þ |
þ |
|
|
|
||
|
Addenda Acknowledged |
þ |
þ |
þ |
þ |
þ |
|
|
|
||
|
Bidder Disclosure Submitted |
þ |
þ |
þ |
þ |
þ |
|
|
|
||
|
Goals met |
|
|
|
|
|
|
|
|
||
|
TOTAL BID AMOUNT:
|
$420,981.75 |
$455,771.00 |
$499,996.25 |
$622,487.00 |
$734,689.16 |
|
|
|
||
|
Bid Rank: |
1 |
2 |
3 |
4 |
5 |
|
|
|
||