DATE:    Friday, October 30, 2009                                    TIME:     11:00 AM

 

CONTRACT NO.:                CE90667 MAIN PROJECT FUNDING NUMBER:           PZ72609_143

 

PROJECT NAME:                2009 SANITARY MASTER PLAN IMPLEMENTATION CIPP

 

PROJECT MANAGER:  Wayne Querry           PHONE:  (303) 446-3641  

 

Engineer’s Estimate:

$3,731,816.80

Prequalification Required:

4c  $5,000,000.00

Number of Addenda:  2

 

BIDS

 

 

MWBE Goals: 6.00%

 

 

 

 

 

 

 

 

Bidders:

SAK Construction, LLC (MO)

RePipe - California, Inc.

Insituform Technologies, Inc.

Western Slope Utilities, Inc. (WSU)

Wildcat Construction Co., Inc.

 

 

 

Bid Guarantee Submitted

þ

þ

þ

þ

þ

 

 

 

Addenda Acknowledged

þ

þ

þ

þ

þ

 

 

 

Bidder Disclosure Submitted

þ

þ

þ

þ

þ

 

 

 

Goals met

 

 

 

 

 

 

 

 

 

TOTAL BID AMOUNT:

 

 

$3,055,073.93

 

$3,173,805.88

 

$3,188,429.48

 

$3,488,975.00

 

$3,694,959.90

 

 

 

 

Bid Rank:

1

2

3

4

5