JOHN W. HICKENLOOPERMayor |
BID SUMMARY |
|||||||||
|
City and County of Denver Department of Public Works Contract Administration 201 West Colfax Dept. 611 Denver, CO 80202 |
DATE: Friday, November 06, 2009 TIME: 11:00 AM
CONTRACT NO.: CE90326 MAIN PROJECT FUNDING NUMBER: PC70809_320
PROJECT NAME: 36th AVENUE - HIGH STREET to CLAYTON STREET STORM SEWER
PROJECT MANAGER: Mike Flick PHONE: (303) 446-3628
|
|||||||||
|
Engineer’s Estimate: $1,084,347.50 |
||||||||||
|
Prequalification Required: 4a $1,500,000.00 |
||||||||||
|
Number of Addenda :1 |
BIDS
|
|||||||||
|
MWBE Goals: 12.00% |
|
|
|
|
|
|
|
|||
|
Bidders: |
Nelson Pipeline Constructors, Inc |
Concrete Works of Colorado, Inc. |
Duran Excavating Inc. |
Arapahoe Utilities & Infrastructure, Inc (A.U.I.) |
Brannan Sand and Gravel Company, LLC |
R & D Pipeline Construction |
BT Construction, Inc. |
|
||
|
Bid Guarantee Submitted |
þ |
þ |
þ |
þ |
þ |
þ |
þ |
|
||
|
Addenda Acknowledged |
þ |
þ |
þ |
NO |
þ |
þ |
þ |
|
||
|
Bidder Disclosure Submitted |
þ |
þ |
þ |
þ |
þ |
þ |
þ |
|
||
|
Goals met |
|
|
|
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
||
|
TOTAL BID AMOUNT:
|
$1,025,695.05 |
$1,030,771.50 |
$1,030,907.50 |
$1,043,753.00 |
$1,055,231.00 |
$1,070,650.00 |
$1,121,721.00 |
|
||
|
Bid Rank: |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
|
||
|
JOHN W. HICKENLOOPER Mayor |
BID SUMMARY |
|||||||||
|
City and County of Denver Department of Public Works Contract Administration 201 West Colfax Dept. 611 Denver, CO 80202 |
DATE: Friday, November 06, 2009 TIME: 11:00 AM
CONTRACT NO.: CE90326 MAIN PROJECT FUNDING NUMBER: PC70809_320
PROJECT NAME: 36th AVENUE - HIGH STREET to CLAYTON STREET STORM SEWER
PROJECT MANAGER: Mike Flick PHONE: (303) 446-3628
|
|||||||||
|
Engineer’s Estimate: $1,084,347.50 |
||||||||||
|
Prequalification Required: 4a $1,500,000.00 |
||||||||||
|
Number of Addenda :1 |
BIDS
|
|||||||||
|
MWBE Goals: 12.00%
|
|
|
|
|
|
|
|
|||
|
Bidders: |
American West Construction |
Reynolds-Tierdael |
T. Lowell Construction, Inc. |
LCI2, Inc. |
Concrete Express, Inc. |
|
|
|
||
|
Bid Guarantee Submitted |
þ |
þ |
þ |
þ |
þ |
|
|
|
||
|
Addenda Acknowledged |
þ |
þ |
þ |
NO |
þ |
|
|
|
||
|
Bidder Disclosure Submitted |
þ |
þ |
þ |
þ |
þ |
|
|
|
||
|
Goals met |
|
|
|
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
||
|
TOTAL BID AMOUNT:
|
$1,149,226.00 |
$1,176,303.00 |
$1,188,000.00 |
$1,212,549.58 |
$1,485,890.20 |
|
|
|
||
|
Bid Rank: |
8 |
9 |
10 |
11 |
12 |
|
|
|
||