Denver Radium Streets

Summary of Remedial Action
2007 Denver Radium Streets Project
Park Avenue

Daily Project Activities:

Date

Project Activity

5/7/07

Conduct project kick-off meeting.  Commence removal oc clean concrete materials along north side of Park Ave. 

 

5/8/07

Conduct daily health and safety meeting. Continue concrete removal. 

 

5/9/07

Conduct daily health and safety meeting.  Pour concrete curb, gutter, and driveways along north side of Park Ave.   

 

5/10/07

Conduct daily health and safety meeting.  Complete concrete demo along south side of Park Ave.

 

5/11/07

Conduct daily health and safety meeting.  Commence  Phase 1 and 2 roto-milling between Arapahoe and Champa.  

 

Photo Log

Radium Scanning Activities Along Park Ave.

 

 

Roto-Milling Clean Asphalt.