Denver Radium Streets

Summary of Remedial Action
2007 Denver Radium Streets Project
9th Avenue

Daily Project Activities:

Date

Project Activity

5/7/07

Traffic Control & Barricades setup; no construction activities scheduled

 

5/8/07

Pre-construction site meeting; no construction activities scheduled

 

5/9/07

Conduct daily health and safety meeting; Tree trimmer removed low branches; Removed, loaded trucks, and hauled contaminated asphalt to waste facility (3 loads)

 

5/10/07

Conduct daily health and safety meeting; Tree trimmer removed low branches; Removed, loaded trucks, and hauled contaminated asphalt to waste facility (6 loads)

 

5/11/07

Conduct daily health and safety meeting; Tree trimmer removed low branches; Removed, loaded trucks, and hauled contaminated asphalt to waste facility (6 loads)

 

 

Photo Log:

 

Tree Trimmer removing low branches

Contaminated asphalt being removed and loaded into lined trucks

 

Contaminated asphalt being removed; dust suppression occurring

 