Public Works Department
Wastewater Management Division - Contract No. CE90724
Parkhill Pond Phase II
Project Funding Number PA77609_323
General Statement of Work
This project entails construction of a storm water detention pond in north Denver, to include removing soil and debris that is
potentially contaminated by asbestos, and construction of a water quality forebay.
View Plan Holder List
Prebid on 11/9/2009 at 9:00 AM
Wastewater Management Division, Conf.
2000 W. 3rd Avenue
Denver, CO 80223
Bid Opening postponed from 11/20/2009 at 11:00 AM to 12/4/2009 at 11:00 AM
1st Floor Conference Room - 1.D.1
201 W. Colfax Ave.
Denver, CO 80202
Plans Available November 02, 2009:
Office of the Cashier
201 W. Colfax, 2nd Floor
Denver, CO 80202
Plan Cost $25.00
Project Manager: Tom Blackman
Phone: (303) 446-3610
Contract Administrator: Teresa Alson
Phone: (720) 913-8528
SBE goal:
DBE goal:
M/WBE goal: 11.00%
FOR COMPLETE DESCRIPTION SEE AD IN The Daily Journal ON THE FOLLOWING DATES:
Monday, November 02, 2009
Tuesday, November 03, 2009
Wednesday, November 04, 2009
THE FOLLOWING PREQUALIFICATIONS ARE REQUIRED
4b Open Channel and Pond
$1,500,000.00