Public Works Department
Wastewater Management Division - Contract No. CE90667
2009 SANITARY MASTER PLAN IMPLEMENTATION CIPP
Project Funding Number PZ72609_143
General Statement of Work
The major item of work to be complete under this project is the rehabilitation of approximately 69,192 linear feet of various size
gravity drained sanitary sewer pipes and 3,780 vertical feet of manholes, with structural deterioration problems, using
Wastewater Management Division approved cured-in-place liner method of construction.
Wastewater Management Division, Conf.
2000 W. 3rd Avenue
Denver, CO 80223
Bid Opening postponed from 10/30/2009 at 11:00 AM to 11/6/2009 at 11:00 AM
1st Floor Conference Room - 1.D.1
201 W. Colfax Ave.
Denver, CO 80202
Plans Available October 05, 2009:
Office of the Cashier
201 W. Colfax, 2nd Floor
Denver, CO 80202
Plan Cost $25.00
Project Manager: Wayne Querry
Phone: (303) 446-3641
Contract Administrator: Teresa Alson
Phone: (720) 913-8528
SBE goal:
DBE goal:
M/WBE goal: 6.00%
FOR COMPLETE DESCRIPTION SEE AD IN The Daily Journal ON THE FOLLOWING DATES:
Monday, October 05, 2009
Tuesday, October 06, 2009
Wednesday, October 07, 2009
THE FOLLOWING PREQUALIFICATIONS ARE REQUIRED
4c Sewer Rehabilitation
$5,000,000.00